(Solution) MOS3330 Homework 18

Additional Algo 18-4 Weighted Shortest Processing Time

A small manufacturer currently has five jobs waiting to be processed. Processing times and importance weights (higher weight implies higher importance) of the jobs are shown below.

JobABCDE
Processing time (minutes)1435353123
Weight (importance)12152

Using the weighted shortest processing time scheduling approach, what is the average inventory of jobs in the system? Assume that processing of jobs will start immediately.

Note: Round your answer to 2 decimal places.

Correct Answer – Additional Algo 18-4 Weighted Shortest Processing Time

Correct Answer 2.86Correct

See full workings at the end of this post.

PA 18-1 (Algo) An architect has five projects to complete…

An architect has five projects to complete. She estimates that three of the projects will require one week to complete and the other two will require three weeks and four weeks. During the time these projects are completed (assume no other projects are worked on during this time.)

What is the architect’s flow rate (projects per week)?

Note: Round your answer to 1 decimal place.

Additional Algo 18-6 Earliest Due Date

A car wash near the mall will wash your car while you are shopping and have it ready when you return. Customers provide the car wash with an estimated return time (due date) and the car wash employees have estimated the time required to complete each car.

JobABCDEF
Due time (minutes)17510013512011580
Processing time (minutes)364830442050

Using the earliest due date scheduling process, what is the average inventory of jobs in the system? Assume that processing of jobs will start immediately.

Note: Do not round intermediate calculations. Round your answer to 2 decimal places.

Additional Algo 18-6 Earliest Due Date

A car wash near the mall will wash your car while you are shopping and have it ready when you return. Customers provide the car wash with an estimated return time (due date) and the car wash employees have estimated the time required to complete each car.

JobABCDEF
Due time (minutes)135160100130145120
Processing time (minutes)374235472749

Using the earliest due date scheduling process, what is the average inventory of jobs in the system? Assume that processing of jobs will start immediately.

Note: Do not round intermediate calculations. Round your answer to 2 decimal places.

Additional Algo 18-2 Integrated Work

At an auto shop, six jobs are currently in queue.

JobABCDEF
Arrival order123456
Processing time (minutes)381533232436

Using the shortest processing time scheduling approach, what is the average inventory of jobs in the system? Assume that processing of jobs will start immediately.

Note: Round your answer to 2 decimal places.

Related: (Solution) MOS3330 Homework 1 – Operations Management

Solution All Questions on MOS3330 Homework 18

A small manufacturer currently has five jobs waiting to be processed. Processing times and importance weights (higher weight implies higher importance) of the jobs are shown below.

JobABCDE
Processing time (minutes)1435353123
Weight (importance)12152

Using the weighted shortest processing time scheduling approach, what is the average inventory of jobs in the system? Assume that processing of jobs will start immediately.

Note: Round your answer to 2 decimal places.

The jobs will be completed in the order D, E, A, B, C. The average processing time is (31 + 23 + 14 + 35 + 35 / 5 = 27.6 minutes  for a flow rate of 1 / 27.6 = 0.0362 jobs per minute.. The average job spends  (31 + 54 + 68 + 103 + 138 / 5 = 78.8 minutes in the system.

Inventory = Flow rate × Flow time = 0.0362 × 78.8 = 2.86 jobs.

JobABCDE
Processing time (minutes)1435353123
Weight (importance)12152
Ratio (Weight / Processing Time)0.0710.0570.0290.1610.087
JobStartDurationFinish
D03131
E312354
A541468
B6835103
C10335138
Average27.678.8